Suncor says Syncrude to ramp up to full production in early to mid-September

Source: The Canadian Press, July 9, 2018 

CALGARY — Suncor Energy Inc. says production at the Syncrude oilsands complex is expected to ramp up to full production in early to mid-September after a power disruption in June that shut down operations.

The company, which holds a 58.7 per cent stake in the partnership, says a preliminary investigation indicates the disruption was caused by a transformer malfunction the cut power on June 20.

It says power and steam systems have been restored and the assessment and repair for the transformer is underway.

Read full article here…